Blocks 3, 4 and 5, on the left, are nearing completion. Blocks 1 and 2, in the distance, have been completed and are being occupied by Years 11 and 12.

The overall status of the building works is as follows:

All structural work – completed. Final payment still to be made.
Blocks 1 and 2 – Finishing work – completed. Final payment still to be made.
Block 3, 4 and 5 – This work is still ongoing but due for completion in the next few months.
It is very heart-warming to see the rapid progress of the construction of the New Academic Block and that completion is due in a matter of months.

 

The top two photos (to left) show the external works on the school building as it stands now in August 2019, as opposed to the two photos below, showing the construction works at the time of our visit in April 2019.

 

 

 

 

 

 

 

 

 

 

Again the photos (to right) show the internal works (completed & cleaned) on a classroom in Blocks 4 and 5 in August 2019 (above) as opposed to ‘under construction’ in April of this year.

 

 

 

 

 

 

 

 

The photographs show a corridor in August 2019 (above) as opposed to April, showing how much progress has been made in the 4 months since the Trustees visited the building site.

 

 

 

 

 

The photograph shows a worker cleaning the staircase in Block 3.

 

 

 

 

 

 

 

 

.

 

The groundworks and drainage are still to be completed.