St Xavier’s Godavari Inaugurates the First Phase of the New Academic Block
We are happy to report the excellent and rapid progress of the construction of the New Academic Block at St Xavier’s Godavari. Blocks 1-2 have been completed sufficiently to enable students to occupy the building and an opening ceremony has been conducted, blessed and...
Construction Status of the New Academic Block – June 2018
Good progress has been made in the construction of Blocks 1 and 2 where classrooms are being completed. Fund raising activities are now focused on Blocks 3, 4 and 5 which is a major section and structural work continues. Blocks 1 and 2
Di Hickey at the Republic Day Ceremony and Nepal Development Conference
Di Hickey describes her experience at the Republic Day and Nepal Development Conference. It was an informative day and a good opportunity to network with many people who have a close relationship and connection with Nepal. I was the first delegate to arrive, so...
The Republic Day Ceremony and Nepal Development Conference
The purpose of the Conference was to celebrate the anniversary of Republic Day on 29 May and to discuss certain the areas of political, social and economic development in Nepal. There were speakers from charities, academia, medicine and the Department for...
Spring Update from Father Samuel
Dear John and JMB Educational Fund Family, Greetings from SXG We are at the end of our Academic year for classes 1-10, Final terminal examination for classes 1-7 and 9 are over and teachers are busy in evaluating the papers. Class 8 is writing their Basic Level...
Construction Status of the New Academic Block – January 2018
The status of the construction of the New Academic Block at St Xavier's School, Godavari in January 2018. Blocks 1,2 and 3 shown above. Actual work on the ground Zero began on 12th June 2017. Prior to the actual concrete work, the school authority had to work on the...
Christmas letter from a sponsored student
A number of our sponsors received Christmas letters from their sponsors this year. We loved them all but particularly liked this one written by Khushi. Click through to read the letter....
Construction Status of the New Academic Block – November 2017
Appeal for the New Academic Block Construction On 30 October 2017 the school Principal Fr Samuel Simick S.J. launched an appeal for funds from the School’s alumni, parents/guardians and other funding sources. This was published on the School’s website as well as...
Construction Status of the New Academic Block – August 2017
Construction work on the New Academic Block at St Xavier's School Godavari, Nepal began in June 2017 with the clearing of the site and the laying of the foundations. However,the planning, design, architectural drawings, project management and approval for the project...